As part of the twinning of the existing 1,150-kilometre Trans Mountain Pipeline built in 1953, Trans Mountain started expansion of its Burnaby Terminal in 2019 with new tanks. Matcon furnished materials and performed installation of four (4) permanent retaining walls in a portion of the tank containment areas requiring shoring.
Following is a summary of the project highlights:
- Committed to the projects Safety Culture ‘Never Walk Past an Unsafe Act or Condition
- Participated in worker and supervisor safety training
- Committed to environmental mitigation measures prior to the start of construction activities
- Committed to the principal quality objectives for the project to meet project requirements, Owners expectations and eliminate rework by performing work ‘Right the First Time’
- Achieved 98%+ score on yearly ISO 9001:2015 audits
- Prepared and updated detailed execution plans for each scope of work
- Pre-production verification test anchor programs
- Responsible for Tier 2 subcontractors
- Collaboration as EPC Subcontractor lead to achieving a Valued Subcontractor status
- Interdisciplinary responsibilities with liner Subcontractor installing the poly urea spray-on liner system integral to the shoring wall system
Scope of Work:
- 28,000 lineal meters of permanent ground anchors
- 20,000 square meters of permanent shotcrete shoring walls
- V-ditch installation
Four (4) Construction Work Areas (CWAs):
1. CWA 201 Firewater Reservoir
2. CWA 206 Secondary Containment
3. CWA 209 Secondary Containment
4. CWA 210 Secondary Containment
See similar projects
Brightside Phases 1 and 3
The project involved various complex tasks such as drilling and installation of cased secant piles, excavation and offsite disposal of soil, installation of tie-back anchors, and shotcrete wall construction.
Learn moreKITS BLOCK - 1981 Macdonald Street, Vancouver
Matcon successfully completed bulk excavation, disposal of contaminated soils, and extensive shotcrete shoring, overcoming challenges posed by hard sandstone with dedicated overtime efforts to maintain the project schedule.
Learn more3619 - 3681 Arbutus Street
Matcon successfully navigated unique challenges, including Vancouver's winter weather and absorbent sandy soils, to complete bulk excavation and shoring, managing running groundwater and implementing face-saving measures within budget and on time.
Learn moreSeymour Village Phase 6
Matcon successfully executed excavation and shoring for the Seymour Village Phase 6 residential project, navigating challenges near active townhome communities with a focus on safety and minimal neighborhood impact.
Learn more