A dynamic project for our environmental division situated along a busy corridor requiring the safe removal of contaminated soil and the destruction and construction of a carpark.

- Commission the excavation and soil retention design
- Temporary re-routing of all utilities within the excavation footprint and temporary removal of light standard
- Excavate to 7m in depth to remove PCE and TCE impacted soils within an operational Safeway carpark
- Excavation, transport and disposal of ~4,300 MT of contaminated soil
- Installation of 3,600 sf shotcrete and shoring
- Drilling and installation of 1,270 lineal ft of soil anchors
- Underpinning Safeway sign
- Slot cut final stage of excavation
- Import, place and compact ~4,100MT of structural backfill
- Reinstate utilities and Carpark
See similar projects

Brightside Phases 1 and 3
The project involved various complex tasks such as drilling and installation of cased secant piles, excavation and offsite disposal of soil, installation of tie-back anchors, and shotcrete wall construction.
Learn more
KITS BLOCK - 1981 Macdonald Street, Vancouver
Matcon successfully completed bulk excavation, disposal of contaminated soils, and extensive shotcrete shoring, overcoming challenges posed by hard sandstone with dedicated overtime efforts to maintain the project schedule.
Learn more
Slate
Matcon successfully executed bulk excavation and shoring for a residential tower in Burnaby, with unique challenges posed by its adjacency to the Millennium Line Skytrain.
Learn more
King George Hub Phase D
Matcon excelled in the excavation and shoring of the King George Hub Phase D project, overcoming challenges posed by the Abbotsford flooding events with a strategic contingency plan for on-time and within-budget delivery.
Learn more