Riverbend Business Park

A multidisciplanry project requiring demolition and environemental to work together.

client
Oxford Properties
client
location
Burnaby
Budget
$
  • Importing clean fill for future construction & pre-load.
  • Removal of 7500 m3 of contaminated soil from a roadway & road reconstruction.
  • Dewatering and decommissioning of a sedimentation pond.
  • Decommissioning of a historical landfill involving removal and screening 7000 m3 of PCB contaminated soil.
  • Decommissioning and removal of more than 4000 m of underground utilities, and approximately 800 m3 of impacted soil.
  • Construction of an on-site landfill for 2500 m3 of impacted soil.
  • Cement stabilization and on-site landfilling of 1000 m3 of metal impacted soil.
  • Bagging and off-site disposal of 1500 m3 of hazardous waste level PCB impacted soil and 2000 m3 of waste level PCB impacted soil.
  • Off-site disposal of screened debris and various levels of impacted soil totaling more than 10,000 m3; on-site landfilling of remaining soil.