Oakridge Park

An incredible opportunity to bring our expertise in demolition and excavation to such a landmark project in Vancouver.

client
Quad Real Property Group
client
location
Vancouver
Budget
$
Scope of Work:
  • Soldier Piles - 9,100ft ┇ Installation of 30’ long W250x67 Soldier piles along the entire West property line due to proximity of newly installed storm line
  • Excavation - 950,000m3
  • Remediation - 40,000m3 ┇ Remediation of contaminated soils from the site
  • Anchors - 245,000ft ┇ Anchors primarily consisted of R32 & R38 Injection Anchors
  • Shotcrete Shoring - 315,000sf ┇ Combination of 4” Shotcrete, 6” Shotcrete, 8” Underpinning
  • DCP Anchors - 15,000ft ┇ Installation of DCP anchors for permanent shotcrete wall
  • DCP Micropiles - 1,500ft ┇ Installation of 50’ long #18 DCP Micropiles for footing seismic considerations
  • Jet Grouting - 10,000ft ┇ Installation of 1.0m diameter jet grout columns. This was required to create a cutoff wall so that core excavation could be completed and not have water issues.
  • Pipe Piles -1,500ft