- Removals of contaminated material.
- Road works including road widening, curbs sidewalk, RMA works, and paving.
- Re & Re of existing 900mm CMP pipe and install new 900mm HDPE pipe.
- Large by-pass system put in place to handle runoff water from Lougheed HWY and all drainage.
- Supply & Install watermain on a high density road.
- Installation of Hydro concrete duct bank, Telus and Shaw conduits.
- Completed work for two client’s side by side onsite to complete the project and keep both parties satisfied and happy.
- Assist with new pump station works at Beta Ave for City of Burnaby.
See similar projects
Brightside Phases 1 and 3
The project involved various complex tasks such as drilling and installation of cased secant piles, excavation and offsite disposal of soil, installation of tie-back anchors, and shotcrete wall construction.
Learn moreKITS BLOCK - 1981 Macdonald Street, Vancouver
Matcon successfully completed bulk excavation, disposal of contaminated soils, and extensive shotcrete shoring, overcoming challenges posed by hard sandstone with dedicated overtime efforts to maintain the project schedule.
Learn moreOakridge Park
An incredible opportunity to bring our expertise in demolition and excavation to such a landmark project in Vancouver.
Learn more