- Removal of Mercury Impacted Soils
- Construction of footings for two solar arrays
- Construction of footings for cable tray associated with solar arrays and wind turbines
- Construction of Battery Shack
- Installation of Cable Tray
- Construction of two wind turbine concrete footings which included the installation and testing of grouted rock anchors to secure the foundation to the bedrock, all reinforcing steel placement, and concrete placement/finishing
- Access to the remote site was via boat, barge or helicopter.
See similar projects
Brightside Phases 1 and 3
The project involved various complex tasks such as drilling and installation of cased secant piles, excavation and offsite disposal of soil, installation of tie-back anchors, and shotcrete wall construction.
Learn moreKITS BLOCK - 1981 Macdonald Street, Vancouver
Matcon successfully completed bulk excavation, disposal of contaminated soils, and extensive shotcrete shoring, overcoming challenges posed by hard sandstone with dedicated overtime efforts to maintain the project schedule.
Learn moreOakridge Park
An incredible opportunity to bring our expertise in demolition and excavation to such a landmark project in Vancouver.
Learn moreLumina Brentwood - 2425 Beta Ave
A dynamic project featuring the tag team efforts of our Civil and Environmental divisions.
Learn more