Matcon was retained to offer perform environemntal servicing as part of the Faro Mine remediation project.

client
Parsons Corporation
client
location
Faro Mine
Budget
$
  • Clear and grub 8,200m2 pipeline corridor
  • Excavate 1,300m3 unsuitable bedding material
  • Screen, haul, place and compact 12,000m3 select fill
  • Install manhole and vacuum breaker
  • Install 75 lin m pipe culvert
  • Install 825lin m 12” insulated HDPE pipe with insulation joint kits
  • Install lock block pipe anchors
  • Post installation pressure testing of HDPE pipeline