Matcon was retained to perform pre-development excavation and slap preparation for handoff as well as install and maintain a siltation / sediment control system.
- 35,000 cubic meters of excavation
- 25,000 square feet of shotcrete shoring
- 13,900 lineal feet of conventional ground anchors
- Supply, install and maintenance of a siltation / sediment control system
- 52,000 square feet of slab preparation
See similar projects
Brightside Phases 1 and 3
The project involved various complex tasks such as drilling and installation of cased secant piles, excavation and offsite disposal of soil, installation of tie-back anchors, and shotcrete wall construction.
Learn moreKITS BLOCK - 1981 Macdonald Street, Vancouver
Matcon successfully completed bulk excavation, disposal of contaminated soils, and extensive shotcrete shoring, overcoming challenges posed by hard sandstone with dedicated overtime efforts to maintain the project schedule.
Learn more3619 - 3681 Arbutus Street
Matcon successfully navigated unique challenges, including Vancouver's winter weather and absorbent sandy soils, to complete bulk excavation and shoring, managing running groundwater and implementing face-saving measures within budget and on time.
Learn moreSeymour Village Phase 6
Matcon successfully executed excavation and shoring for the Seymour Village Phase 6 residential project, navigating challenges near active townhome communities with a focus on safety and minimal neighborhood impact.
Learn more