Our environmental division played a pivotal role in the predevelopment stages of this project, managing and containing contaminated sites surrounding the development.
- Installation of 500, 1 m diameter, 9m deep (4500 M2) cased secant piles to form an impermeable barrier wall to isolate the site from the surrounding contaminated sites
- Excavation, management and disposal of ~1,500 MT of large slag from historic foundry operations
- Excavation and on-site screening of ~5,500 M3 of contaminated soil/debris to separate the soil and debris
- Off-site transport and disposal of ~11,000 MT of contaminated soil and debris for disposal
- Installation of a whaler and tie-back anchors to allow the secant pile wall to act an excavation shoring face
- Pumping of contaminated water to a water treatment system prior to discharge
See similar projects
Brightside Phases 1 and 3
The project involved various complex tasks such as drilling and installation of cased secant piles, excavation and offsite disposal of soil, installation of tie-back anchors, and shotcrete wall construction.
Learn moreKITS BLOCK - 1981 Macdonald Street, Vancouver
Matcon successfully completed bulk excavation, disposal of contaminated soils, and extensive shotcrete shoring, overcoming challenges posed by hard sandstone with dedicated overtime efforts to maintain the project schedule.
Learn more3619 - 3681 Arbutus Street
Matcon successfully navigated unique challenges, including Vancouver's winter weather and absorbent sandy soils, to complete bulk excavation and shoring, managing running groundwater and implementing face-saving measures within budget and on time.
Learn moreSeymour Village Phase 6
Matcon successfully executed excavation and shoring for the Seymour Village Phase 6 residential project, navigating challenges near active townhome communities with a focus on safety and minimal neighborhood impact.