- Underground twin sewer main installation on arterial and onsite roads at 4-5m deep
- Earthworks- Removal of 20,000m3 of disposal and Import of 35,000mt of gravel for the completion of the underground utilities and roadworks
- Supply & Install - Hydro/Tel/Shaw & trenching for Fortis
- Installation of Infiltration Gallery, street lighting
- Installation of porous concrete driveways