Situated along a busy corridor, this site required extensive excavation and remediation efforts before any pre-development slab work could commence.

- Bulk/Detail Excavation of 70,000m3 of soils
- Remediation of contaminated soils
- Installation of 3,500’ of 4” Pipe Piles
- Installation of 55,000sf of Shotcrete shoring & 40,000ft of tieback anchors
- Backfilling of adjacent park area with 13,000m3 of native material form the excavation
- Installation of precast barrels and drain tile
See similar projects

Brightside Phases 1 and 3
The project involved various complex tasks such as drilling and installation of cased secant piles, excavation and offsite disposal of soil, installation of tie-back anchors, and shotcrete wall construction.
Learn more
KITS BLOCK - 1981 Macdonald Street, Vancouver
Matcon successfully completed bulk excavation, disposal of contaminated soils, and extensive shotcrete shoring, overcoming challenges posed by hard sandstone with dedicated overtime efforts to maintain the project schedule.
Learn more
Slate
Matcon successfully executed bulk excavation and shoring for a residential tower in Burnaby, with unique challenges posed by its adjacency to the Millennium Line Skytrain.
Learn more
King George Hub Phase D
Matcon excelled in the excavation and shoring of the King George Hub Phase D project, overcoming challenges posed by the Abbotsford flooding events with a strategic contingency plan for on-time and within-budget delivery.
Learn more